1 preparation:
(1) Heating asphalt pump half an hour in advance,
heating asphalt pool two hours in advance.
(2) Manually running
the parts of asphalt plant.
(3) Check whether all valves are in working
status, manually take oil, preheating asphalt pipeline and measuring tank until
the normal work.
2 Powers:
(1) Heating asphalt pump, this can be
closed after half an hour.
(2) Stir to open.
(3) Open the air compressor.
(4) Start dusting motor.
(5) Igniter.
(6) High-pressure diesel pump.
(7) Observe whether the ignition is
successful, three unsuccessful must stop to check..
(8) Start blower motor.
(9) Start the main pump.
(10) The drying drum should be opened by
manual operation.
3 The production process:
(1) Drum drying.
(2) Elevate ore hopper.
(3) Drop by ore hopper.
(4) Waiting for three minutes (wet material
for three minutes, dry material about one minute) to be good material drying.
(5) On the screen, click taking asphalt, spraying
asphalt, taking powder, add powder. Stir for two minutes.
(6) The finished hopper down to the
finished product tank.
(7) Elevate the finished product hopper;
open the storage silos to discharge.
(8) Elevate ore hopper.
4 Shutdowns:
(1) Shut down the main oil pump and
high-pressure diesel pump.
(2) Close other moving parts, keep drying
drum, draft fan, drum fan to run.
(3) Cleaning asphalt pump, piping and asphalt
measuring tank.
(4) Waiting for furnace and roller cooling,
turn off all motors.
(5) Disconnect the power.